Seal Beach Pump Station Replacement

Home >> Construction >> Seal Beach Pump Station Replacement

Construction work continues for a new pump station in the City of Seal Beach.  This work ensures the new pump station will operate reliably for decades to come and meet OC San’s mission to protect public health and the environment by providing effective wastewater collection, treatment, and recycling.

Recent Photos

Seal Beach Pump Station drone shot. August 2025.

View from above.

Seal Beach Pump Station ground level view. Sept 2025.

View from the ground level.

Seal Beach Pump Station looking into wet well. Sept 2025.

View looking below ground.

Ongoing Work

Location:  Northeast corner of Seal Beach Blvd. and Westminster Ave., Seal Beach

What’s Happening:  Crews continue excavation to prepare the site for the new pump station.

Progress: Excavation has been taking place to get to the 50-foot depth for the new pump station’s wet well.  A pump station wet well is a large underground tank that collects, stores, and pumps sewage into the sewer system.

Schedule: Ongoing – Fall 2025*

Impacts:

  • One northbound lane on Seal Beach Blvd. remains closed.
  • Truck traffic entering and exiting the site continues.

*All dates and times are subject to change due to operational factors or inclement weather. 

Project Description

This project will replace the OC San Seal Beach Pump Station located at the corner of Seal Beach Blvd. and Westminster Ave. in the City of Seal Beach. The new station will be upgraded to new local, state, and national codes as well as have enhanced security measures. The new facility will also have an added odor control system installed.

Project Background

The Seal Beach Pump Station was originally constructed in 1972.  The pumping systems are aging, regularly clog, lack corrosion protection, and have control systems that are rapidly becoming obsolete, all requiring additional attention from maintenance staff.

Additional Information

The bus stop located in front of the pump station on Seal Beach Blvd. at Westminster Ave. has been removed (see picture below) for the duration of the project. Please visit OCTA for alternative routes.

Stay In The Know

Community Liaison:
(714) 378-2965

Email:
constructionhotline@ocsan.gov

Sign up for text alerts:
click here

Site Location

Construction Schedule

Spring 2024 - Spring 2028

Construction Budget

$97 million